Budget
$2,500,000
Architect
Wiltshire Swain Pty Ltd
Builder
Tonkin Schutz Design & Build
Construction commenced
1/11/2017
Construction completed
19/10/2018
Key improvements
-
The STEM hub will provide an innovative, flexible learning environment that encourages creativity, imagination and innovation within refurbished space.
-
Space on the ground level and first level of the science, general teaching and disability unit building will be refurbished. A new internal stair case will provide a visual and circulatory link between the two levels.
-
The adjacent outdoor courtyard will link to the recently re-developed learning hub located on the ground level of the building. Transparency and seamless transition between internal and external zones and between floors allow for effective collaboration, peer learning, research and the sharing of information.
Project timeline
Architect appointed
Planning study completed
Builder appointed
Construction commenced
Construction completed
Contact
STEM Works Team
Phone: 8226 1578