Address
90 Hart Street
Semaphore South 5019 SA
http://www.lefevrehs.sa.edu.au/
Budget
$2,500,000
Architect
Chapman Herbert Architects Pty Ltd
Builder
Hansen Yuncken Pty Ltd
Construction commenced
11/12/2017
Construction completed
16/08/2018
Key improvements
- The existing science labs will be refurbished into modern, purpose-built facilities, which can be combined to create larger multi-purpose and adaptable learning spaces.
- The outdoor learning areas will complement current STEM activities including naval testing, floatation and propulsion. IT will allow broadening of the curriculum to feature robotics and maritime testing.