Go to top of page

Millicent North Primary School

Address

Second Street
Millicent 5280 SA
http://www.millnthps.sa.edu.au/

Budget

$1,000,000

Architect

Grieve Gillett Pty Ltd

Builder

Steplen Constructions Pty Ltd

Construction commenced

9/01/2018

Construction completed

28/06/2018

Key improvements

  • The STEM learning area will be centrally located for all students to access to ensure that learning opportunities are maximised and seamlessly integrated into daily activities.
  • This space will enable students to engage in collaborative learning in break out spaces and create opportunities for students to access a 'maker' space as part of general class activities as well as programmed STEM class time using investigation, creation and experimentation using digital media as well as physical media.  Adaptable and flexible modular furniture will be used in collaborative spaces to utilise spaces in a variety of ways.
  • Outdoor learning in both an open and protected space will enhance the learning experiences for students and provide space for construction materials and work 'in progress' storage.

Project timeline

Construction completed

Architect appointed

Planning study completed

Builder appointed

Construction commenced

Construction completed

Contact

STEM Works team

Phone: 8226 6559
Emaileducation.STEMWorks [at] sa.gov.au