Budget
$1,000,000
Architect
Michael Watson Architect
Builder
Minuzzo Project Management
Construction commenced
15/08/2017
Construction completed
20/12/2017
Key improvements
- A range of neighbouring spaces will be opened up and refurbished to provide a wet area, dry laboratory, digital teaching and a maker space. The new area will further provide break out space with connection to an external covered outdoor classroom.
- The new outdoor teaching facility will include a large open space with sinks which will enable students to enquire and test environmental factors such as sun, wind and rain.
Project timeline
Construction completed
Architect appointed
Planning study completed
Builder appointed
Construction commenced
Construction completed
Contact
STEM Works Team
Phone: 8226 1578
Email: education.STEMWorks [at] sa.gov.au