Initial concept plans for the capital works at Urrbrae Agricultural High School for their upgrade have been released.

Plans have been reviewed in line with the transition of year 7 into high school by 2022.

Among the upgrades being considered for Urrbrae Agricultural High School are:

  • Construction of a Health and Wellbeing building to include home economics, physical education teaching space and an agricultural learning square.
  • Construction of a new building to provide additional learning areas for year 7s, including music space.
  • Extension and renovation of the gymnasium to remove the mezzanine level and provide additional seating to enable whole of school assemblies.
  • Demolition of ageing infrastructure.

These plans are subject to further consideration and may change.

Budget

$10m

Architect

Matthews & Partners Pty Ltd Architects

Builder

Cook Building and Development Pty Ltd

Project timeline

Construction commenced

Architect appointed

Builder appointed

Construction commenced

Construction completed